Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

A critical activity is a . an activity that consumes no time but shows precedence between events. b . an activity with zero slack. c

A critical activity is
a. an activity that consumes no time but shows precedence between events.
b. an activity with zero slack.
c. the beginning of an event.
d. a milestone accomplishment within the project.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Students also viewed these General Management questions