a) Draw a network diagram for the project and calculate the fastest time in whcih the following project may be completed. Act Description Duration (Days)

a) Draw a network diagram for the project and calculate the fastest time in whcih the following project may be completed.

Act Description Duration (Days) Predecessor
A Develop project deliverables 15 -
B Approval from stakeholders 5 A
C select site 4 B
D evaluate and select vendor 4 B
E purchase hardware 3 D
F design software 15 B
G write code 30 F
H test software 4 G
I test hardware 10 E
J integrate hardware and software 20 H, I
K install and final acceptance 5 C, J

B) What is the end date if the start date is 25 June 2016?

c) What is the effect of B slipping by 3 days?

d) Explain any two measures that you would take to ensure that the project is completed on schedule?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Expert Oracle9i Database Administration

Authors: Sam R. Alapati

1st Edition

1590590228, 978-1590590225

More Books

Students also viewed these Databases questions

Question

What is cost plus pricing ?

Answered: 1 week ago

Question

1. What are the types of wastes that reach water bodies ?

Answered: 1 week ago

Question

Which type of soil has more ability to absorb water?

Answered: 1 week ago