a) Draw a network diagram for the project and calculate the fastest time in whcih the following project may be completed. Act Description Duration (Days)
a) Draw a network diagram for the project and calculate the fastest time in whcih the following project may be completed.
Act | Description | Duration (Days) | Predecessor |
A | Develop project deliverables | 15 | - |
B | Approval from stakeholders | 5 | A |
C | select site | 4 | B |
D | evaluate and select vendor | 4 | B |
E | purchase hardware | 3 | D |
F | design software | 15 | B |
G | write code | 30 | F |
H | test software | 4 | G |
I | test hardware | 10 | E |
J | integrate hardware and software | 20 | H, I |
K | install and final acceptance | 5 | C, J |
B) What is the end date if the start date is 25 June 2016?
c) What is the effect of B slipping by 3 days?
d) Explain any two measures that you would take to ensure that the project is completed on schedule?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started