A) Draw the project network with Normal time. What is the project completion date? And cost? B) What is the probability that the project will
A) Draw the project network with Normal time. What is the project completion date? And cost?
B) What is the probability that the project will be completed in 18 weeks
C) Find the ES, EF, LS, LF, SLACK & crash cost per week for each activity.
D) Reduce the project cycle time by five weeks (Crash the network by five weeks). And identify the new critical path.
E) Find the new cost of completing the project (after crashing).
F) Determine how soon we can finish the project (Crash the network until no further crashing). And identify the new critical path and new project total cost.
G ) Develop ESEF Gantt chart for this project after crashing ( completing F).
As received. please help
Develop a solution for the following project problem. Crash Crash Cost Normal Time Act Pred. Time (total) (Weeks) Normal Cost A 4 $800 7 $500 B 2 $350 3 $200 A,B 4 $900 6 $500 D 1 $500 3 $200 E B 1 $550 2 $300 Develop a solution for the following project problem. Crash Crash Cost Normal Time Act Pred. Time (total) (Weeks) Normal Cost A 4 $800 7 $500 B 2 $350 3 $200 A,B 4 $900 6 $500 D 1 $500 3 $200 E B 1 $550 2 $300Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started