Question
A facility is trying to set up an assembly line and has identified the various tasks and their relationship to each other, as shown in
A facility is trying to set up an assembly line and has identified the various tasks and their relationship to each other, as shown in the following table. The managers want to produce 600 units per day, working two 8-hour shifts.
Task | Previous task | Time to complete (sec.) |
A | -- | 20 |
B | -- | 30 |
C | -- | 25 |
D | -- | 10 |
me | A | 55 |
F | D, B, C | 30 |
GRAMS | me | 25 |
H | F, G | 40 |
(a) Draw a network diagram of precedence relationships.
(b) Calculate the cycle time required per unit in seconds.
(c) Calculate the minimum number of workstations required to produce 600 units per day.
(d) Balance this line using the longer processing time heuristic.
(e) What is the efficiency of the line obtained in part (d)?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get StartedRecommended Textbook for
Managerial Decision Modeling With Spreadsheets
Authors: Nagraj Balakrishnan, Barry Render, Jr. Ralph M. Stair
3rd Edition
136115837, 978-0136115830
Students also viewed these General Management questions
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
View Answer in SolutionInn App