A fastener production unit has a bolt manufacturing cell. The cell has three workstations, a milling station, a drilling station, and a packing station. The
A fastener production unit has a bolt manufacturing cell. The cell has three workstations, a milling station, a drilling station, and a packing station. The milling station has five parallel millers, with a natural capacity of partshour each. The drilling station has three parallel drills, with a natural capacity of partshour each. The packing station has a single manual packer with a natural capacity of partshour
The milling station is maintained every hours and the maintenance lasts hours. The drilling station is maintained every hours and the maintenance lasts hours. The packer is never down during a shift and is therefore available all the time. Note: the availability calculated may be assumed to apply to the entire station and no need to apply them to each machine individually.
What is the critical workinprocess in this manufacturing cell?
If bolts have to be completed each hour, arrivals following an exponential distribution, and the squared coefficient of variation of process times for the milling, drilling, and packing stations are and respectively:
Calculate the total time it takes for a bolt to be completed.
Calculate workinprocess in the manufacturing cell.
Is the WIP calculated in part B different from the critical WIP calculated in question Explain the reason for the difference.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started