Question
1 Approved Answer
A firm has the NPV of a project based on three possible economic conditions and their probabilities given below. The expected NPV is $40.3 million.
A firm has the NPV of a project based on three possible economic conditions and their probabilities given below. The expected NPV is $40.3 million. What is the standard deviation for the project NPVY T A Economic condition Probability of outcome NPV (5 million) 1 50 21 Recession Boom 30 70 No change 20 44 20.02 21.30 O 23.00 1981