A Firm needs a rolling-horizon planning model for determining the optimal numbers of temporary personnel to hire to minimize cost over Months 3 thru 5
A Firm needs a rolling-horizon planning model for determining the optimal numbers of temporary personnel to hire to minimize cost over Months 3 thru 5 (though also, because of hiring arrangements, there are implied costs in Months 6 and 7, but these implied costs are treated as irrelevant to determining an optimal hiring plan).
There are two types of temps hired - 1-month ["1M"] and 3-month ["3M"].Those hired of either type require up-front training (at a cost to ABC of $500 per person); their monthly pay is as follows:
1M - $75003M - 6300
ABC has known staffing complements/commitments for the three types of personnel (long-term ["LT"], 1M, and 3M) - for 1Ms and 3Ms, for both a current month ["month 1"] and the following month ["month 2"], and for LTs, over an entire five month span - and needs to make optimal decisions for the 1M and 3M hires in Months 3, 4, and 5 to meet the known staffing requirements [stated in units of "staff-month"].
An illustration of the known staffing situation for a hypothetical month 1 is as follows:
Month:1 (This)2 (Next)345
LT63345
1M77# to hire?# to hire?# to hire?
3M 221+# to hire?# to hire?# to hire?
Known Staff-Month
Need:1512141512
(NOTE:All the specific values shown are part of the illustration.Actual month-to-month use of the model will involve entry of such values as ABC plan in "rolling time horizon" style.)
Unlimited numbers of 1M and 3M applicants exist; with respect to timing of hiring, there are limits on the number of hired 3Ms as follows:
Month:345
Limit:(no limit)32
Beyond Month 5 - i.e., for Months 6 & 7 - there need to be at least two 3Ms but not more than three.Costs in Months 6 & 7 are not considered relevant to the optimization.
To achieve a "smoother" pattern of required personnel, there is the possibility of shifting required staff-months of work between months 4 & 5.The limit in such shifting is that only up to four staff-months can be shifted either way.The cost of making shifts is as follows:
From Month 4 to Month 5:$3,000/staff-month
From Month 5 to Month 4:$5,000/staff-month
These costs, if incurred, are considered relevant to the optimization
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started