Answered step by step
Verified Expert Solution
Link Copied!
Question
1 Approved Answer

Given the network below and the activities' three-time estimates, answer the following questions: Activity A 0/0/0 Activity B 18/30/72 Activity C 45/61/131 Activity D

Given the network below and the activities three-time estimates, answer the following questions: a. If the contract for a pr 

Given the network below and the activities' three-time estimates, answer the following questions: Activity A 0/0/0 Activity B 18/30/72 Activity C 45/61/131 Activity D 24/36/90 Activity E 12/18/48 Activity F 6/15/54 Activity G 0/0/0 a. If the contract for a project is 120 days, what is the chance (in percent) of meeting the schedule? b. Assume the owner delays the job start by 5 days. What is the probability (in percent) that the project will still finish at the originally scheduled completion date? c. What is the probability (in percent) of not meeting the original schedule? d. What is the probability (in percent) of completing the project in 90 days? e. What is the project completion date with at least a 90% confidence level?

Step by Step Solution

3.28 Rating (145 Votes )

There are 3 Steps involved in it

Step: 1

The detailed answer for the above question is provided below a If the contract for a project is 120 days what is the chance in percent of meeting the ... blur-text-image
Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Accounting

Authors: Jonathan E. Duchac, James M. Reeve, Carl S. Warren

23rd Edition

978-0324662962

More Books

Students explore these related General Management questions