Given the network below and the activities' three-time estimates, answer the following questions: Activity A 0/0/0 Activity B 18/30/72 Activity C 45/61/131 Activity D
Given the network below and the activities' three-time estimates, answer the following questions: Activity A 0/0/0 Activity B 18/30/72 Activity C 45/61/131 Activity D 24/36/90 Activity E 12/18/48 Activity F 6/15/54 Activity G 0/0/0 a. If the contract for a project is 120 days, what is the chance (in percent) of meeting the schedule? b. Assume the owner delays the job start by 5 days. What is the probability (in percent) that the project will still finish at the originally scheduled completion date? c. What is the probability (in percent) of not meeting the original schedule? d. What is the probability (in percent) of completing the project in 90 days? e. What is the project completion date with at least a 90% confidence level?
Step by Step Solution
3.28 Rating (145 Votes )
There are 3 Steps involved in it
Step: 1
The detailed answer for the above question is provided below a If the contract for a project is 120 days what is the chance in percent of meeting the ...See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started