A form of progressive elaboration planning where the work to be accomplished in the near term is planned in detail at a low level of
A form of progressive elaboration planning where the work to be accomplished in the near term is planned in detail at a low level of the WBS, while work far in the future is planned for WBS components that are at a relatively high level of the WBS, is called: Select one: a. Rolling wave planning. b. Detailed planning. c. Long-term planning. d. Magnified planning