A general contractor has a contract to construct the water line for a new subdivision. The original estimate for the water line was $158,000 and

A general contractor has a contract to construct the water line for a new subdivision. The original estimate for the water line was $158,000 and no changes have been made to the budget. The water line has been installed by the general contractor itself and the costs to date for the water line are $187,000 and it is estimated that it will take another $24,000 to complete the water line.

What is the total estimated cost of the water line at completion for the general contractor?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Students also viewed these Accounting questions