A given work package has a planned valuel (PV) of $10,000 , an earned value (EV) of $9,000 , and an actual cost (AC) of
A given work package has a planned valuel (PV) of
$10,000
, an earned value (EV) of
$9,000
, and an actual cost (AC) of
$12,000
. Which of the following is not true:\ Cost variance is
-$3,000
\ Schedule variance is
-$2,000
\ Cost performance index is 0.75\ Schedule performance index is 0.9