A given work package has a planned valuel (PV) of $10,000 , an earned value (EV) of $9,000 , and an actual cost (AC) of

A given work package has a planned valuel (PV) of

$10,000

, an earned value (EV) of

$9,000

, and an actual cost (AC) of

$12,000

. Which of the following is not true:\ Cost variance is

-$3,000

\ Schedule variance is

-$2,000

\ Cost performance index is 0.75\ Schedule performance index is 0.9

image text in transcribed
A given work package has a planned valuel (PV) of $10,000, an earned value (EV) of $9,000, and an actual cost (AC) of $12,000. Which of the following is not true: Cost variance is $3,000 Schedule variance is $2,000 Cost performance index is 0.75 Schedule performance index is 0.9

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

More Books

Students also viewed these Finance questions