A is usually not necessary to the Scrum method, because Scrum implies that team members work as a self - directed group. velocity estimate Gantt
A is usually not necessary to the Scrum method, because Scrum implies that team members work as a selfdirected group.
velocity estimate
Gantt chart
product backlog
team charter