A job was budgeted to require 3 hours of labor per unit at $8.00 per hour. The job consisted of 8,000 units and was completed
A job was budgeted to require 3 hours of labor per unit at $8.00 per hour. The job consisted of 8,000 units and was completed in 22,000 hours at a total labor cost of $198,000. What is the total labor cost variance? 1)$6,000 unfavorable. 2)$3,000 unfavorable. 3)$8,000 unfavorable. 4)$9,000 unfavorable. 5)$2,000 unfavorable