Question

1 Approved Answer

A job was budgeted to require 3 hours of labor per unit at $11.00 per hour. The job consisted of 8,000 units and was completed

A job was budgeted to require 3 hours of labor per unit at $11.00 per hour. The job consisted of 8,000 units and was completed in 22,000 hours at a total labor cost of $269,500. What is the direct labor efficiency variance?

Multiple Choice

$27,500 unfavorable.

$22,000 unfavorable.

$16,000 unfavorable.

$22,000 favorable.

$6,000 unfavorable.

I get confused when the questions ask for the direct labor rate variance or the direct labor efficiency variance. Is it the same thing? Please explain. Thank you!!

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Intermediate Accounting

Authors: Loren A. Nikolai, John D. Bazley, Jefferson P. Jones

11th edition

978-0538467087, 9781111781262, 538467088, 1111781265, 978-0324659139

More Books

Students also viewed these Accounting questions

Question

What do we do well in working together?

Answered: 1 week ago