A job was budgeted to require 3 hours of labor per unit at $8.00 per hour. The job consisted of 8,100 units and was completed
A job was budgeted to require 3 hours of labor per unit at $8.00 per hour. The job consisted of 8,100 units and was completed in 20,300 hours at a total labor cost of $198,000. What is the direct labor efficiency variance?
Multiple Choice
$32,000 favorable.
$32,000 unfavorable.
$35,600 unfavorable.
$3,600 unfavorable.
$35,600 favorable.
Step by Step Solution
There are 3 Steps involved in it
Step: 1