A job was budgeted to require 5 hours of labor per unit at $9.00 per hour. The job consisted of 6,000 units and was completed
A job was budgeted to require 5 hours of labor per unit at $9.00 per hour. The job consisted of 6,000 units and was completed in 27,000 hours at a total labor cost of $274,800. What is the direct labor efficiency variance?
Multiple Choice
$31,800 unfavorable.
$31,800 favorable.
$27,000 unfavorable.
$27,000 favorable.
$4,800 unfavorable.
Step by Step Solution
There are 3 Steps involved in it
Step: 1