A job was timed for 60 cycles and had an average of 1.27 minutes per piece. The performance rating was 87 percent, and workday
A job was timed for 60 cycles and had an average of 1.27 minutes per piece. The performance rating was 87 percent, and workday allowances are 11 percent. Determine each of the following: a. Observed time. (Round your answer to 2 decimal places.) Observed time minutes b. Normal time. (Round your answer to 2 decimal places.) Normal time minutes