Question
1 Approved Answer
A job was timed for 60 cycles and had an a range of 1.2 minutes per piece. the performance rating was 95% and workday allowance
A job was timed for 60 cycles and had an a range of 1.2 minutes per piece. the performance rating was 95% and workday allowance s are 10% , determine observed time, normal and standard time