Question

1 Approved Answer

A job was timed for 60 cycles and had an average of 1.3 minutes per piece. The performance rating was 95 percent, and workday allowances

A job was timed for 60 cycles and had an average of 1.3 minutes per piece. The performance rating was 95 percent, and workday allowances are 17 percent. Determine each of the following:

a.Observed time.(Round your answer to 1 decimal place.)

Observed timeminutes

b.Normal time.(Round your answer to 2 decimal places.)

Normal timeminutes

c.Standard time.(Round your answer to 2 decimal places.)

Standard timeminutes

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Making Hard Decisions with decision tools

Authors: Robert Clemen, Terence Reilly

3rd edition

538797576, 978-0538797573

More Books

Students also viewed these Mathematics questions