Question

1 Approved Answer

A labor crew for placing concrete consists of one labor foreman at $26.09 per hour, one cement finisher at $29.30 per hour, 4laborers at $24.45

A labor crew for placing concrete consists of one labor foreman at $26.09 per hour, one cement finisher at $29.30 per hour, 4laborers at $24.45 per hour each, and one equipment operator at $34.9 per hour. Such a crew, called a C20 crew, can place 160 cubic yards of concrete per 8-hour day.

Determine the cost per day of labor for the C20 crew.

The cost per day is determined to be $.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Microeconomics

Authors: Douglas Bernheim, Michael Whinston

2nd edition

73375853, 978-0073375854

More Books

Students also viewed these Economics questions

Question

Behaviour: What am I doing?

Answered: 1 week ago