Question

1 Approved Answer

A large renovation of the Hard Rock casino has six activities (in weeks). The estimated times and immediate predecessors are given in the following table

A large renovation of the Hard Rock casino has six activities (in weeks). The estimated times and immediate predecessors are given in the following table (a=Optimistic, m=most likely, b= pessimistic times). Assume that the activity times are independent:

Time

Activity

Immediate predecessor(s)

a

m

b

A

-

11

15

19

B

-

27

31

41

C

-

18

18

18

D

A,B

9

10

11

E

C

5

8

11

F

D,E

16

19

22

a) Determine the total expected project completion time.

b) What is the critical path of the project?

Select one:

a) 42 weeks; b) C-E-F

a) 59 weeks; b) A-D-F

a) 61 weeks; b) B-D-F

a)61 weeks; b) A-B-D-F

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Development Economics In The Twenty-First Century

Authors: Claudia Sunna, Davide Gualerzi

1st Edition

1317219961, 9781317219965

More Books

Students also viewed these Economics questions

Question

6. How can hidden knowledge guide our actions?

Answered: 1 week ago

Question

7. How can the models we use have a detrimental effect on others?

Answered: 1 week ago