A large Saskatchewan feed mill, B. Swart Processing, prepares its sixty-month aggregate plan by forecasting demand for 50-pound bags of cattle feed as follows: January,

A large Saskatchewan feed mill, B. Swart Processing, prepares its sixty-month aggregate plan by forecasting demand for 50-pound bags of cattle feed as follows: January, 1000 bags; February, 1200; March, 1250; April, 1450; May, 1400; and June, 1400. The feed mill plans to begin the new year with no inventory left over from the previous year, and backorders are not permitted. It projects that capacity (during regular hours) for producing bags of feed will remain constant at 800 until the end of April, and then increase to 1100 bags per month when a planned expansion is completed on May 1. Overtime capacity is set at 300 bags per month until the expansion, at which time it will increase to 400 bags per month. A friendly competitor in Alberta is also available as a backup source to meet demandbut can provide only 500 bags total during the six-month period.

Develop a six-month production plan for the feed mill using the transportation method.

Cost data are as follows:

Regular-time cost per bag (until April 30) $12.00

Regular-time cost per bag (after May 1) $11.00

Overtime cost per bag (during entire period) $16.00

Cost of outside purchase per bag $18.50

Carrying cost per bag per month $ 1.00

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Students also viewed these General Management questions