A logical network is shown. Now a new activity of Schedule Inspector must precede Inspect machine, a new activity of Group Operator must precede Train
A logical network is shown. Now a new activity of "Schedule Inspector" must precede
"Inspect machine", a new activity of "Group Operator" must precede "Train Operator".
Add the new activities to the network without causing faulty dependency