A manager of your Company. ask your advice to evaluate 3 projects, consider the following information to determine the project the manager should be select
A manager of your Company. ask your advice to evaluate 3 projects, consider the following information to determine the project the manager should be select by the following criterias:
1- Risk-Adjusted Discount Rate RADR 2- Equivalent Certainty Factor CF
Projects | A | B | C |
Cost | 100000 | 150000 | 200000 |
Expected of cash inflows | 20000 | 25000 | 30000 |
Life( years) | 7 | 9 | 10 |
Level of risk ( c.v) | 0.24 | 0.34 | 0.18 |
company usually uses the following discount rates 10%, 7%, 12%, and certainty factors 0.633, 0.742, 0.543
Risk free rate 5%
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started