A manager wants to assign tasks to workstations to achieve an hourly output rate of 3 3 units. Assume that the shop works 6 0
A manager wants to assign tasks to workstations to achieve an hourly output rate of units. Assume that the shop works minutes per hour ie no breaks
a Assign the tasks shown in the following precedence network times are on the nodes and are in minutes to workstations using the following heuristic rules:
i Assign the task with the most followers.
ii Tiebreaker: assign the task with the longest time.
b What is the efficiency?