A manager wants to assign tasks to workstations to achieve an hourly output rate of 33 units. Assume that the shop works 60minutes per hour
A manager wants to assign tasks to workstations to achieve an hourly output rate of 33 units. Assume that the shop works 60minutes per hour (i.e., no breaks). L05
- Assign the tasks shown in the following precedence network (times are on the nodes and are in minutes) to workstations usingthe following heuristic rules: (i) "Assign the task with the most followers." (ii) Tiebreaker: "Assign the task with the longesttime."
- What is the efficiency?