A manufacturing company is designing an assembly line to produce its main product. The line should be able to produce 50 units per hour. The

A manufacturing company is designing an assembly line to produce its main product. The line should be able to produce 50 units per hour. The following data in the Table give the necessary information.

Task Immediate Predecessor Task Time (sec)
A None 34
B A 51
C A 21
D B 38
E C 25
F D, E 59
G F 16

Which task is the bottleneck?

Task select a bottleneck task

is the bottleneck.

eTextbook and Media

Select the appropriate precedence diagram for the above information.

eTextbook and Media

Compute the cycle time with a desired output of 50 units per hour.

C = enter cycle time in seconds per unit seconds/unit

eTextbook and Media

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Operations Management in the Supply Chain Decisions and Cases

Authors: Roger Schroeder, M. Johnny Rungtusanatham, Susan Goldstein

6th edition

73525243, 978-0073525242

More Books

Students also viewed these General Management questions