Question

1 Approved Answer

A manufacturing company is designing an assembly line to produce its main product. The line should be able to produce 30 units per hour. The

A manufacturing company is designing an assembly line to produce its main product. The line should be able to produce 30 units per hour. The following data in the Table give the necessary information.

Task Immediate Predecessor Task Time (sec)
A None 34
B A 50
C A 21
D B 39
E C 26
F D, E 59
G F 15

Which task is the bottleneck?

Task select a bottleneck task FACDBGE is the bottleneck.

eTextbook and Media

Select the appropriate precedence diagram for the above information.

Compute the cycle time with a desired output of 60 units per hour.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Managing Operations Across The Supply Chain

Authors: Morgan Swink, Steven Melnyk, Janet L. Hartley, M. Bixby Cooper

4th Edition

1260547639, 978-1260547634

More Books

Students also viewed these General Management questions

Question

7 Describe the role of an HR business partner

Answered: 1 week ago

Question

5 Explain the concept of the psychological contract.

Answered: 1 week ago