A manufacturing company is designing an assembly line to produce its main product. The line should be able to produce 30 units per hour. The
A manufacturing company is designing an assembly line to produce its main product. The line should be able to produce 30 units per hour. The following data in the Table give the necessary information.
Task | Immediate Predecessor | Task Time (sec) | ||
---|---|---|---|---|
A | None | 34 | ||
B | A | 50 | ||
C | A | 21 | ||
D | B | 39 | ||
E | C | 26 | ||
F | D, E | 59 | ||
G | F | 15 | ||
Which task is the bottleneck?
Task select a bottleneck task FACDBGE is the bottleneck.
eTextbook and Media
Select the appropriate precedence diagram for the above information.
Compute the cycle time with a desired output of 60 units per hour.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started