A marketing research firm has received requests from 3 new clients. It has 3 people available to lead these projects: Yareli, Joanne and Lin. The
A marketing research firm has received requests from 3 new clients. It has 3 people available to lead these projects: Yareli, Joanne and Lin. The following table gives the estimated project completion times in days for each client/worker combination:
Decision variables Client Objective function: Project 1 manager Yareli 10 Joanne 9 Lin 6 Constraints 2 15 18 14 3 555 The three projects have approximately the same priority, and each project leader is assigned to one and only one project. Each project needs one and only one leader. How should the project managers be assigned to minimize total completion time? 9 This is similar to the transportation problem. The difference here is that the 'supply' is the number of project leaders each individual can provide. Each person can provide 1 project leader. Each client requires 1 and only 1 project leader. You can think of the amount "shipped' as 1 project manager or 0 project managers, depending on whether or not the person works for a particular client. Use dimensional analysis as usual. Diagram 3 Put your linear program into solver and solve it. State which project manager will work for which client, and what the total hours worked will be.
Step by Step Solution
★★★★★
3.47 Rating (163 Votes )
There are 3 Steps involved in it
Step: 1
We draw the assignment diagram as shown below The objective of the function is to minimize the dur...Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started