A mason and a helper lay 150 concrete blocks during a 10-hour day. The mason is paid $14.50 per hour and the helper $8.00 per
A mason and a helper lay 150 concrete blocks during a 10-hour day. The mason is paid $14.50 per hour and the helper $8.00 per hour. What is the labor cost per concrete block? (There is no overtime) 1. $1.50 2. $1.00 3. $0.96 4. $0.53