A measurement analyst selects measures for the Information Need Evaluate the status of the software design activity and see whether design activities are being completed
- A measurement analyst selects measures for the Information Need "Evaluate the status of the software design activity and see whether design activities are being completed as scheduled." Based on the evaluation criteria Measurement Results Fitness for Purpose, are the selected measured provided in Table 5 of the Supplementary worksheet relevant to decision making?
- No, because the measures are not directly related to design process
- Yes, because the measures are taken on a regular basis
- No, because the measures do not satisfy assumptions in the model
- Yes, because the measures identify design progress
Table 5:
Entities and Attributes | |
Relevant Entities |
|
Attributes |
|
Base Measure Specification | |
Base Measures |
|
Measurement Methods |
|
Type of Method |
|
Scale |
|
Type of Scale |
|
Unit of Measurement |
|
Derived Measure Specification | |
Derived Measure | Percent of design units completed |
Measurement Function | Divide the design units that have completed design by the design units planned for each period and multiply by 100 |
Indicator Specification | |
Indicator Description and Sample | Design Completion - graph the two base measures (planned design units complete, actual units complete) over time, plus include a data table with the derived measure (percent complete). |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started