Question

1 Approved Answer

A mini project was estimated to cost $25,000 and to be completed on 15 December 2009. The calculated actual cost at the end of September

A mini project was estimated to cost $25,000 and to be completed on 15 December 2009. The calculated actual cost at the end of September 2009 is $18,500. The remaining 20 percent work is to be completed as soon as possible to maintain the completion due date.

(a) What are the cost and schedule variances at this stage? (b) If the original project duration was 18 months and total budget was $35,000, Calculate the estimated cost of completion and estimated time to complete.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Multinational Management

Authors: John B. Cullen

6th edition

1285094946, 1285094948, 9781285696744 , 978-1285094946

More Books

Students also viewed these General Management questions