A national conference is planned in a college. The activities are listed down along with their predecessors and time taken. Prepare a network diagram and
A national conference is planned in a college. The activities are listed down along with their predecessors and time taken. Prepare a network diagram and determine the critical activities.
tableActivityDescription,tableImmediatePredecessorDuration daysAConfirm lead speaker and topic,BPrepare brochure,CSend letters to other speakers,BDGet confirmation from speakers,CESend letters to participants,CDFObtain travel plans from speakers,DGArrange for accommodation for speakers,FHGet handouts from speakers,FIFinalize registrations,GHJArrange hall and AVI,KConduct of programme,J
Ims.kku.edu.sa
For the PERT problem find the critical path and project duration. What is the probability that the project will be completed in days?
tableActivityPredecessor,TimeOptimisticMost likely,PessimisticABCADAECFDGBHEFIG
The following table lists the jobs of a network along with their estimates.
tableActivityTime WeeksCost RsNormalCrash,Normal,Crash
a Draw the project network diagram.
b Calculate the length and variance of the critical path.
c What is the probability that the jobs on the critical path can be completed in days?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started