A network consists of the activities in the following list. Times are given in weeks. Activity Preceding Time A -- 8 B -- 4 C
A network consists of the activities in the following list. Times are given in weeks. Activity Preceding Time A -- 8 B -- 4 C A 3 D B 3 E A, D 3 F C, E 4 What is the project completion time if there is no delay