Activity | Predecessor | Duration |
A | - | 8 |
B | - | 3 |
C | A | 7 |
D | A,B | 3 |
E | C | 4 |
F | D | 6 |
A. | Path: B-C-E, Duration: 17 weeks | |
B. | Path: A-D-E Duration: 17 weeks | |
C. | Path: A-D-E Duration: 19 weeks | |
D. | Path: A-C-E Duration: 19 weeks |