A new order filling system needs to be installed as soon as possible. The table on the next page lists that projects activities and their

A new order filling system needs to be installed as soon as possible. The table on the next page lists that projects activities and their predecessors. Also provided is the cost information to reduce the standard activity times. (problem 7-32 in the textbook)

(a) Construct a project network for this problem. Determine the EST, EFT, LST, LFT, and slack for each activity. Also determine the critical path and project completion time.

(b) Set up and solve an LP model using Excel to crash this project to 24 days. What is the total crashing cost?

ACTIVITYIMMEDIATE PREDECESSORSSTANDARD TIME (Days)STANDARD COSTCRASH TIME (Days)CRASH COSTA--7$2,0005$3,500BA10$3,0008$4,700CA8$3,4007$3,700DC6$1,6004$2,600EC7$1,9004$4,000FD,E5$1,2003$2,800GB,C11$8,2008$10,900HF,G4$2,6003$3,800

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Project Management A Systems Approach to Planning Scheduling and Controlling

Authors: Harold Kerzner

10th Edition

978-047027870, 978-0-470-5038, 470278706, 978-0470278703

More Books

Students also viewed these General Management questions