A new product development project has the following characteristics: There are three main tasks. Task A must be delivered 4 weeks before task C starts.
A new product development project has the following characteristics:
There are three main tasks.
Task A must be delivered 4 weeks before task C starts.
Once task B is finished, task C will start.
What is the relationship between tasks A and B? Select one. Question 2 options:
A. Finish-to-start (FS)
B. Finish-to-finish (FF)
C. Start-to-start (SS)
D. Start-to-finish (SF)