A Northern British Columbia lumberyard has four jobs on order, as shown in the following table. Today is day 2 0 5 on the yard's

A Northern British Columbia lumberyard has four jobs on order, as shown in the following table. Today is day 205 on the yard's schedule.
The first day the task arrives is the first day that the job is being done.
In what sequence would the jobs be ranked according to the following decision rules:
a) FCFS
b) SPT
c) LPT
d) EDD
e) Critical ratio
Which is best and why? Which has the minimum lateness?
a) Using the FCFS (first come, first served) decision rule for sequencing the jobs, the order is (assume that jobs came in the order in which they are listed in the table):
The average tardiness (job lateness) for the sequence developed using the FCFS rule is days (round your response to two decimal places).
The average completion time for the sequence developed using the FCFS rule is days (round your response to two decimal places).
The percentage utilization for the sequence developed using the FCFS rule is %(enter your response as a percentage rounded to two decimal places).
b) Using the SPT(shortest processing time) decision rule for sequencing the jobs, the order is(to resolve a tie, use the order in which the jobs were recieved.
The average tardiness(job lateness) for the sequence developed using the SPT rule is
enter your response here days (round your response to two decimal places).
Part 14
The average completion time for the sequence developed using the SPT rule is
enterour response here days (round your response to two decimal places).
The percentage utilization for the sequence developed using the SPT rule is _____ enter your response here%(enter your response as a percentage rounded to two decimal places).
c) Using the LPT(longest processing time) decision rule for sequencing the jobs, the order is(to resolve a tie, use the order in which the jobs were received):
Part 17Part 18Part 19
Sequence
Job
1
A
B
C
D
2
C
D
B
A
3
C
D
A
B
4
D
A
B
C
Part 20
The average tardiness(job lateness) for the sequence developed using the LPT rule is
enter your response here days (round your response to two decimal places).
Part 21
The average completion time for the sequence developed using the LPT rule is
enter your response here days (round your response to two decimal places).
Part 22
The percentage utilization for the sequence developed using the LPT rule is
enter your response here%(enter your response as a percentage rounded to two decimal places).
Part 23
d) Using the EDD(earliest due date) decision rule for sequencing the jobs, the order is(to resolve a tie, use the order in which the jobs were received):
Part 24Part 25Part 26
Sequence
Job
1
D
A
C
B
2
A
C
B
D
3
C
B
A
D
4
D
A
C
B
Part 27
The average tardiness(job lateness) for the sequence developed using the EDD rule is
enter your response here days (round your response to two decimal places).
Part 28
The average completion time for the sequence developed using the EDD rule is
enter your response here days (round your response to two decimal places).
Part 29
The percentage utilization for the sequence developed using the EDD rule is
enter your response here%(enter your response as a percentage rounded to two decimal places).
Part 30
e) Using the Critical Ratio(CR) scheduling rule for sequencing the jobs, the order is:
Part 31Part 32Part 33
Sequence
Job
1
D
A
C
B
2
D
C
A
B
3
B
A
C
D
4
A
C
D
B
Part 34
The average tardiness(job lateness) for the sequence developed using the CR rule is
enter your response here days (round your response to two decimal places).
Part 35
The average completion time for the sequence developed using the CR rule is
enter your response here days (round your response to two decimal places).
Part 36
The percentage utilization for the sequence developed using the CR rule is
enter your response here%(enter your response as a percentage rounded to two decimal places).
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Fundamentals of Management

Authors: Robbins, DeCenzo, Coulter

7th Edition

132996855, 0-13-610982-9 , 9780132996853, 978-0-13-61098, 978-0136109822

More Books

Students also viewed these General Management questions

Question

QUESTION:- Hypertension- drugs, normal values?

Answered: 1 week ago

Question

Human brain is also known as the emotional brain?

Answered: 1 week ago