A planned factory expansion project has an estimated initial cost of $800,000. Based on a discount rate of 20%, the present value of the future
A planned factory expansion project has an estimated initial cost of $800,000. Based on a discount rate of 20%, the present value of the future cost savings from the expansion is $843,000. To yield exactly a 20% return on investment, the actual investment expenditure should not exceed the $800,000 estimated cost by more than what amount?