A plant receives an order to process a batch of components with $100000. The estimated processing and other operating costs are $75000. The materials required
A plant receives an order to process a batch of components with $100000. The estimated processing and other operating costs are $75000. The materials required to complete the order are ready. The plant spent $40000 in total to purchase the materials. But the price of these materials has dropped to $20000. (15 points) Decide accept or not accept the order and explain why.