A process uses four machines called A, B, C, and D to produce their two products called X and M. Product X sells for $10

A process uses four machines called A, B, C, and D to produce their two products called X and M. Product X sells for $10 and product M sells for $15. The table shows how long each product is processed on each machine. Each machine is available for 8 hours per day and the company has demand for 15 Xs and 20 Ms. Machine Product X Product M A 15 min/unit 15 min/unit B 25 min/unit 5min/unit C 20 min/unit 10 min/unit D 10 min/unit 20 min/unit What is the best product mix for the company?

Machine

Product X

Product M

A

15 min/unit

15 min/unit

B

25 min/unit

5 min/unit

C

20 min/unit

10 min/unit

D

10 min/unit

20 min/unit

What is the best product mix for the company?


Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Introduction To Materials Management

Authors: Arnold J. R. Tony, Gatewood Ann K., M. Clive Lloyd N. Chapman Stephen

8th edition

9386873249, 134156323, 978-9386873248

More Books

Students also viewed these General Management questions

Question

Describe dehumidification and why is it needed in buildings.

Answered: 1 week ago

Question

What functions does the MPS perform between sales and production?

Answered: 1 week ago