A process works for 6 hours a day and has a capacity of 42 units per day. A customer calls to place an order when
A process works for 6 hours a day and has a capacity of 42 units per day. A customer calls to place an order when there are 210 orders already in process in the system. a. What is the cycle time for this process? b. How long will it take to clear the backlog in front of this new order