A product owner selected a number of user stories with a total of 1 1 0 points for the next release. Knowing that the team

A product owner selected a number of user stories with a total of 110 points for the next release. Knowing that the teams velocity is 20 story points, whats the estimated duration to complete the release?
Its not possible to calculate the estimated number of sprints to complete a release in agile
5 sprints
6 sprints
5.5 sprints