Question

1 Approved Answer

A production line at Generic Corp's has 5 stations. The first can process a unit in 11 minutes. station one then feeds station two, which

A production line at Generic Corp's has 5 stations. The first can process a unit in 11 minutes. station one then feeds station two, which takes 7 minutes. Station three then begins and operates simultaneously with station two. Station 3 takes 12 minutes. Both stations two and three feed station four which can process a unit in 9 minutes. Station four then feeds station five (the final assembly point), which takes 15 minutes.

a. Which is the bottleneck station?

b. How much time is the bottleneck?

c. What is the throughput time for one unit to go through the process?

d. What is the daily capacity if the company operates 2 shifts (8 hours per shift)?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Introduction To Hospitality Management

Authors: John R Walker

3rd Edition

0135061385, 9780135061381

More Books

Students also viewed these General Management questions

Question

confirm the correct answers

Answered: 1 week ago