Question
1 Approved Answer
A production line is to be designed for a job with three tasks. The task times are 0.6 minutes, 0.8 minutes, and 1.4 minutes. The
A production line is to be designed for a job with three tasks. The task times are 0.6 minutes, 0.8 minutes, and 1.4 minutes. The minimum cycle time in minutes is