A production process for flower vases consists of three tasks to be completed in sequence: first, Shape ( by a specialized machine ) , second,
A production process for flower vases consists of three tasks to be completed in sequence: first, Shape by a specialized machine second, Bake in a single oven and third, Paint by a worker The times taken for one vase at each step are minutes for Shape, minutes for Bake, and minutes for Paint. There are working hours in each day.
Assume that there is one resource at each step and there is no waiting time between steps.
Question at position
points
Question at position
What is the daily capacity of each activity a Shape b Bake, and c Paint. Show calculations.
What is the daily capacity of each activity a Shape b Bake, and c Paint. Show calculations.
p
Question at position
points
Question at position
Which is the bottleneck task, and why?
Which is the bottleneck task, and why?
p
Question at position
points
Question at position
If the demand for flower vases is units per day, what will be the flow rate per day of the original process?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started