Question
A professor has been contacted by four not-for-profit agencies that are willing to work with student consulting teams. The agencies need help with such things
A professor has been contacted by four not-for-profit agencies that are willing to work with student consulting teams. The agencies need help with such things as budgeting, information systems, coordinating volunteers, and forecasting. Although each of the four student teams could work with any of the agencies, the professor feels that there is a difference in the amount of time it would take each group to solve each problem. The professor's estimate of the time, in days, is given in the table below.
Projects | ||||
Team | Budgeting | Information | Volunteers | Forecasting |
A | 32 | 35 | 15 | 27 |
B | 38 | 40 | 18 | 35 |
C | 41 | 42 | 25 | 38 |
D | 45 | 45 | 30 | 42 |
- Determine which team should be assigned to which project to minimize total time.
- Team C just informed us that they cannot participate. How would this change your original solution? Show your results below.
- Since team C is no longer available, which of the two new teams (X or Y shown below) should be selected to minimize total time. Show your results below.
Team | Budgeting | Information | Volunteers | Forecasting |
X | 42 | 32 | 19 | 47 |
Y | 37 | 43 | 16 | 34 |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started