A program has 20% branch instructions of which 60% are not taken branches. what is the effective speedup we could obtain from a 5 stage
A program has 20% branch instructions of which 60% are not taken branches. what is the effective speedup we could obtain from a 5 stage pipeleine if we use predict not taken with branch penality of 3 ? Assume ideal CPI is 1.
1)3.03
2)3.82
3)4.03
4)5.02
5) none of the above