A Project Assistant has the responsibility of coming UP with a time estimate for a Work Package. The WP has 3 serial activities each 5

A Project Assistant has the responsibility of coming UP with a time estimate for a Work Package. The WP has 3 serial activities each 5 days in duration. An estimator is performing the duration for the WP and is nervous about the WP duration being too short, so the estimator increases the "most likely" activity durations by 23%, and sends it to the Project Assistant. The assistant decides to add an additional 2 days to the WP estimate received, because they want to make sure enough time is allocated in the WP to get all the activities done. The revised estimate is forwarded to the PM who adds yet anothgy 2 days. By what % does the final WP estimate exceed the "most likely" estimate? 

Step by Step Solution

3.42 Rating (152 Votes )

There are 3 Steps involved in it

Step: 1

Given Original activity duration for each of the 3 serial activities 5 days each Estimator increases ... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Business Forecasting With Forecast X

Authors: Holton Wilson, Barry Keating, John Solutions Inc

6th Edition

73373648, 978-9339220426, 9339220420, 978-0073373645

More Books

Students also viewed these Accounting questions

Question

25.0 m C B A 52.0 m 65.0 m

Answered: 1 week ago