A project being analyzed by PERT has 55 activities, 8 of which are on the critical path. If the estimated time along the critical path

A project being analyzed by PERT has 55 activities, 8 of which are on the critical path. If the estimated time along the critical path is 125 days with a project standard deviation of 15 days, find the project deadline that gives this project a 23% chance of on-time completion. (Use NORMAL CURVE AREAS table in APPENDIX I of the textbook.)

Group of answer choices from

113.96 to 114.08 days from 113.84 to 113.96 days from 114.2 to 114.32 days from 113.72 to 113.84 days from 114.08 to 114.2 days

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Business Research Methods

Authors: Alan Bryman, Emma Bell

3rd Edition

0199583404, 9780199583409

More Books

Students also viewed these General Management questions